Key statistics
| Countries | Producing fields | 2012 Working interest production | % of Group production | % oil/gas |
|---|---|---|---|---|
| 4 | 38 | 21,350 | 27% | 0/100 |
In 2012, average working interest production was 21,350 boepd predominantly from the Southern North Sea assets in the UK and Netherlands with the remainder from the Bangora field in Bangladesh.
In May 2011, Tullow significantly enhanced its Dutch portfolio though the acquisition of Nuon Exploration & Production from the Vattenfall Group for a cash consideration of €300 million ($432 million). This is a non-operated portfolio of gas producing fields, a range of exploration opportunities and an equity interest in infrastructure.
In March 2012, Tullow announced its intention to sell the Groups Asia assets and Southern North Sea assets in the UK and Netherlands.
| Country | Asset | Interest | 2012 Actual |
2013 Forecast |
Fiscal Regime |
|---|---|---|---|---|---|
| Netherlands | Various | 4.1-22.5% | 6,350 | 5,200 | |
| Norway | Brage | 2.5% | - | 250 | |
| UK | CMS Area2 | 14.1-100% | 9,300 | 10,400 | Tax |
| Thames Area | 50-87% | 750 | 50 | Tax | |
| Total | 16,400 | 15,900 | |||
| Bangladesh | Bangora | 30% | 4,915 | 4,050 | PSC |
| Pakistan | Shekhan-1 | 40% | 35 | 0 | - |
| Total | 4,950 | 4,050 | |||
*Data from latest fact book.
| Country | Developments |
Sanction Decision |
First Production |
No. of Wells | Status |
|---|---|---|---|---|---|
| Netherlands | Joint Development Area (JDA) wells | 2013-2015 | Q1 2013 – 2015 | 6-7 | NAM operated wells using Swift rig and back-to-back drilling. |
| L-15-A Infill | 2013-2015 | Q3 2013 | 3 | 1 well per year over next 3 years. | |
|
UK CMS Area |
Schooner Infill |
|
Q3 2013 | 1 | SA-11 Infill well, Schooner field. |
| CMS, Boulton Field Infill | 2013 | 2014 | 1 | In planning. | |
| Bangladesh | Bangora Workovers |
|
2013 | 2 | Workovers of existing wells to replace tubing and add perforations to restore plateau rate to 100-120 mmscfd. |
| Bangora Phase 3 |
|
2014 | n/a | Installation of compression to maintain plateau production at 100-120 mmscfd and increase recovery. | |
| Bangora South | 2013 | 2015 | 1+ | Southern satellite to Bangora Field awaiting drilling sanction. | |
| Pakistan | Kohat Block | 2013 | 2014 | TBC | Possible appraisal or development decision following Shekhan Extended Well Test, and acquisition and interpretation of seismic data. |
| Kalchas Block |
|
2014 | 1+ | First well (Marri-1) planned for 2013 to be followed by appraisal programme in the event of success. | |
| Norway1 | Brage infill |
|
Producing | 4 – 5 infill | Ongoing production infill well drilling campaign through 2013/14, following rig upgrades due in Q1 2013. Operator change from Statoil to Wintershall awaiting approval from authorities, but expected early 2013. |
| Bream | End 2013 | 2017 | 7 | Licence extension pending. Development plan due to be submitted in Dec 2013. Leased FPSO development scheme currently envisaged. Upto five producers and two water injectors currently planned. | |
| Butch | 2015 | 2018 | 10+ | Two firm appraisal wells to be drilled in Q3/Q4 2013. PDO deadline Q1 2016. Development concepts currently range from subsea tieback to standalone facility. | |
1 Portfolio management of non core developments will be reviewed
*Data from latest fact book.