Ghana Flag of Ghana

Last updated: 30 Jul 2014

Production

Key statistics

Producing fields 1H 2014 Working interest production (boepd) % of Group production % oil/gas 2014 Forecast production (boepd)
1 36,600 47% 100/0 35,800

The start of 2011 saw the first lifting of Jubilee crude oil from the FPSO Kwame Nkrumah. Following the strong operating performance of the Kwame Nkrumah FPSO, Tullow, on behalf of the Jubilee Partners, acquired the FPSO from Modec on 29 December 2011. This acquisition will enable the Jubilee Partners to maximise the FPSO’s commercial value and operational efficiency whilst Modec will continue to provide operations and maintenance services.

The Jubilee Phase 1 development was completed in October 2011 when the last of the initial 17 wells were drilled, completed and brought on stream.

In 2011, gross production from the Jubilee field averaged 66,000 bopd, reaching 88,000 bopd before declining to approximately 70,000 bopd at the end of the year. Production from the field was below expectations due to reduced productivity in a number of wells. The issue, which did not impact the level of field reserves or resources, was remdiated through a work programme successfully carried out in 2012 to regain well productivity. Acid stimulations was identified as the optimum solution to return the wells to their original productivity and a number of these were successful completed in 2012 with production in early 2013 at around 110,000 bopd.

Throughout 2013, the reservoir performance continued to be strong and the Phase 1A infill wells were being completed as required and will continue to be completed as required during 2014. Planning work also continues on additional development and drilling opportunities that will significantly extend the field plateau. The first planned maintenance shutdown of the Jubilee FPSO Kwame Nkrumah was successfully completed in late September 2013. The field production was impacted during the second half of 2013 due to a number of unplanned shutdowns of the FPSO’s water injection system. The system is now fully operational and reservoir pressure has been restored. 

The onshore gas processing facilities, which will allow for the offtake of Jubilee associated gas, are expected to be completed in the fourth quarter of 2014. A bypass line is also being pursued to route a limited quantity of offshore gas directly to the power plant when the gas processing plant is under maintenance or not available for operation. In addition, approval was granted by the Ghana Environmental Protection Agency to permit the flaring of 500 mmscf of gas per month from the field until the end of October 2014. This limited flaring will help maintain current production rates while we await start-up of the main gas processing facility which will then allow a ramp up of production from the Jubilee field towards the facility capacity of 120,000 bopd.

The TEN Project is Tullow’s second operated development offshore Ghana and will combine production from the Tweneboa, Enyenra and Ntomme fields. On 29 May 2013, the Government of Ghana formally approved the Development Plan. This paved the way for Tullow and its partners to proceed with the development and to define the final schedule and capital programme, with the aim of delivering first oil by mid-2016 and enabling a steady ramp up to an expected gross capacity production rate of 80,000 bopd by 2017. Provisions for gas export are also included in the development plan. The development includes the drilling and completion of up to 24 development wells which will be connected through subsea infrastructure to an FPSO vessel. Development drilling commenced in 2014 and to date eight of the ten wells expected to be on stream at start-up have now been drilled. The overall cost of the development remains at around $4.9 billion, excluding FPSO lease costs. The process to partially farm-down Tullow’s interest in the project is on-going.

The project is progressing well with 30% now complete, all major contracts awarded, Tullow delivery teams in place and all work permits ready for installation works to begin in 2015. The conversion of the Centennial Jewel trading tanker into the TEN FPSO continues on schedule at the Jurong Shipyard in Singapore.

Tullow has already completed the drilling of the Enyenra-6A and Ntomme-4A (Nt-04) water injection wells to better determine the oil-water contacts in each of the Enyenra and Ntomme fields. The Enyenra-6A appraisal well was completed in April 2013 after encountering 18 metres of oil pay indicating a deeper than expected oil water contact in the field. The Nt-04 well also indicated a slightly deeper oil water contact and good reservoir development, supporting our decision to add water injection facilities to the Ntomme development. An injectivity test at Nt-04 is currently being performed to confirm lateral connectivity of the target reservoirs. The wells will both be suspended for future use in the TEN development programme. A 3D seismic programme is expected to be completed over the TEN and Wawa fields by the end of the first quarter of 2014.

Following the expiry of the Deepwater Tano Exploration Licence on 18 May 2013, the remaining non-prospective acreage has been relinquished and the Jubilee Unit Area, the TEN Development and Production Area and the Wawa Discovery Area have been retained.

Production Summary - Key producing assets

2014 Development opportunities

Ghana share listing

The Tullow Oil plc Ghana share offer has been a success with over 3.5 million shares allotted. Trading of Tullow shares on the GSE commenced on 27 July 2011.