Key statistics
| Countries | Producing fields | 2012 Working interest production boepd | % of Group production | % oil/gas |
|---|---|---|---|---|
| 6 | 19 | 57,750 | 73% | 100/0 |
Tullow has production in six African countries across 19 fields. The majority of the 57,750 boepd average working interest production in 2012 came from Ghana, Equatorial Guinea and Gabon. West and North Africa accounted for over 70% of the Group's total production and is set to increase in 2013 as Jubilee production increases versus 2012.
| Working interest production boepd | |||||
|---|---|---|---|---|---|
| Country | Asset | Interest | 2012 Actual |
2013 Forecast |
Fiscal Regime |
| Congo (Brazz) | M'Boundi | 11% | 2,500 | 2,400 | PSC |
| Côte d'Ivoire | Espoir | 21.30% | 3,400 | 4,000 | PSC |
| Equatorial Guinea | Ceiba | 14.25% | 2,850 | 3,500 | PSC |
| Okume | 14.25% | 8,350 | 6,200 | PSC | |
| Gabon | Tchatamba | 25% | 4,000 | 4,000 | PSC |
| Niungo | 40% | 2,500 | 2,100 | Tax | |
| Etame Complex1 | 7.50% | 1,450 | 1,100 | PSC | |
| Others | - | 6,050 | 6,800 | Various | |
| Ghana | Jubilee | 35.48% | 25,450 | 37,750 | PSC |
| Mauritania | Chinguetti | 22.25%2 | 1,300 | 1,200 | PSC |
| Total Africa | 57,850 | 69,050 | |||
1. Etame / Avouma / Ebouri
| Country | Developments |
Sanction Decision |
First Production |
No. of Wells |
Status |
|---|---|---|---|---|---|
|
Congo (Brazzaville) |
M'Boundi Field Re-development |
|
Producing | 14+ wells p.a | Continued infill drilling with 2 rigs, including appraisal of recent SE MBoundi field extension. Gas reinjection project to be commissioned in H2 2013. |
| Côte d'Ivoire | Acajou appraisal | 2014 | 2016 | 1-2 | Satellite discovery near Espoir field. |
| Espoir Infill Drilling |
|
Q2 2013 | 8 + 4 | First 8-well project sanctioned and drilling operations commence Q1. Second 4-well project proceeding towards approval. | |
|
Equatorial Guinea |
Ceiba infill drilling |
|
Q2 2012 | 7 + 3 WO |
First 6 producers based upon 4D seismic added 18 mb/d gross production during 2012. Up to 4 more wells due on line, concluding the campaign by end 2013. |
| Deep water Okume Complex Infill drilling |
|
Q4 2013 | 8-12 | New-build tender assisted rig to drill 12 wells from Foxtrot TLP and then Echo TLP, plus 1 subsea producer tie-back. Rig due to arrive Q3 2013. | |
| Shallow water Okume Complex Infill drilling | 2013 | Q4 2014 | 4-8 | Jackup rig infill wells on Elon field in 2014, quantity to be determined from ongoing 4D seismic analysis. | |
| Gabon | Ebouri/Avouma (Etame complex) |
|
Q1 2013 | 3 workovers + 2 pilots & horizontals if successful + 1 Exploration | Commenced drilling Avouma producer, followed by 3 workovers, plus Ebouri appraisal well. Sanctioned development on SEENT field with new wellhead platform for 2014, plus new Etame wellhead platform for 2014. Template drilling to take place 2014. |
| Echira Infill | Q4 2013 | H1 2014 | 1 | Infill drilling scheduled for Q1 2014. | |
| Limande Re-development |
|
Q3 2013 | 5 | Four producers plus 1 gas injector commencing mid 2013, using same rig as Tchatamba. | |
| Niungo Infill |
|
Q4 2012 | 1 + 7 USRs | First 2 ultra short radius (USR) side-tracks added 1.5 mb/d. Niungo Deep Appraisal well in progress, followed by up to 5 more USR’s during 2013. | |
| Onal- Maroc Nord Development |
|
Producing | 18 wells per year | Development drilling at Maroc North and Onal in progress. 3D seismic under review to optimise infill targets. | |
| Tchtamba – Marin and South Infill |
|
Q2 2013 | 4 | Two producers at Marin platform Q2 2013, followed by 2 at South platform Q4 2013. | |
| Tsiengui |
|
Producing | > 20 prod | Phase 2 drilling commenced Q2 2011 (3 year program). Gas injection scheme being implemented. | |
| Turnix |
|
Q2 2013 | 2 | First well scheduled Q2 2013, using same rig as Limande and Tchatamba. | |
| Ghana | Jubilee Phase 1a |
|
Q4 2012 | 8 | Infill wells using existing and additional subsea infrastructure. Designed to raise recovery and extend plateau with 5 extra producers and 3 water injectors. First production achieved Q4 2012. Project completion by end 2013 with all wells on-line. |
| Jubilee Full Field | 2013 onwards | 2014-20 | 10-20 | Incremental development consisting of additional infill wells and subsea infrastructure to further raise recovery and maintain plateau production levels. A Full Field Development Plan (FFDP) is being discussed with the Government. Additional subsea tree equipment (long lead items) has been ordered. | |
| West Cape Three Points (Teak, Mahogany-East, Akasa) | 2014 | 2016-21 | 4-6 | Development possibilities are under discussion with Partners and Government, and development plan submission may follow. Tie-back in to Jubilee facilities is likely plan. | |
| Tweneboa/Enyenra/Ntomme (T.E.N) | 2013 | 2016 | 23 | Plan of Development (PoD) submitted to Government of Ghana in November 2012. Plan approval process underway. First oil timing 32-36 months post plan approval. | |
| Mauritania | Banda Gas | 2014 | 2016 | 2 | Development plan for gas scheme approved by Mauritanian Government in Q4 2012. Front end engineering work complete. Sanction will take place when gas sales agreement is in place. Active engagement underway. |
*Data from fact books.