The integrated project team

Jubilee Deepwater Development logo

Established in February 2008 to prepare the Jubilee Plan of Development and deliver a fully commissioned field development system.

GNPC

Ghana’s National oil company, a field partner and national regulator

Tullow Oil plc

Unit operator of the Jubilee Phase 1 development

KOSMOS Energy

US exploration company. Technical operator of the Jubilee Phase 1 project

Anadarko

Large independent US E&P company with proven deepwater project capabilities and a major contributor to the team

Sabre Oil and Gas

Privately owned exploration company

EO Group Ltd

Ghanaian oil company

  • Previous page
  • Next page

3.5 years from discovery to first oil

In 2007, based on the results of the first two exploration wells, the Jubilee field partners and the Government of Ghana jointly took the early decision to proceed with the development of the Jubilee field. An Integrated Project Team (IPT) was rapidly assembled, bringing together major deepwater skills and experience from across the partnership. In parallel, Tullow quickly developed a deepwater development drilling capability and a total of 16 wells have been drilled to date. First oil is scheduled for the fourth quarter of 2010, representing a record time from discovery to delivery of major deepwater production.

The Jubilee field

Jubliee field location map

Our journey to first oil and beyond

  • Start here

July 2009
Phase 1 Development Plan and field unitisation approved